Background Image
Table of Contents Table of Contents
Previous Page  18 / 88 Next Page
Information
Show Menu
Previous Page 18 / 88 Next Page
Page Background

Truck and Track

Spring 2019

www.truckandtrack.com

18

BUSINESS NEWS

Utilising our Nooteboom triple extendable Super Wing

Carriers, deliveries of the 78 turbine blades (26 turbines in

total) destined for Kype Muir Wind Farm are now complete.

Our Teams undertook the planning and delivery of 494 components

including blades, towers, nacelles, drive trains and hubs required

for the development of Kype Muir Wind Farm. The 80m hub height

towers of the Senvion 3.4MW turbines feature 52m blades, and

whilst these are not the largest we’ve been appointed to handle,

they necessitated the use of our Super Wing Carriers due to the

problematic road restrictions and alignments en-route.

Several areas of route modifications were identified ahead of the

commencement of the project, this included bridge restrictions,

with an emphasis on the Lambhill Road and Brown’s Bridge areas

on approach to the site. Excluding the loaded wind turbine blades,

each of the components would be loaded to a combination of 3, 4,

5 & 6 axle stepframes, modular low loaders and clamp trailers for

transportation to site and with the planned route modifications,

including removal of vegetation, road signage and road widening,

already having been completed this would not pose a great

challenge to navigate.

The challenge arose when it came to the transportation of the 52m

blades, which is where our Super Wing Carriers came into effect.

The use of these specialist trailers provided us with the ability to

shorten the body and wheelbase of the trailer whilst loaded with

the use of the bolster arrangement on the trailer deck. Utilising

the features of these Super Wing Carriers, extendable up to 64.3m,

meant that the proposed access route to the development site

became a viable option for this size of turbine.

Proof of this flexibility was demonstrated prior to transport by

Collett Consulting creating a 3D model of the loaded vehicle. This

then allowed us to produce a detailed swept path analysis video

of the blade components successfully negotiating restricted route

sections by manipulating the trailer whilst loaded.

This in-depth planning allowed us to highlight the sections of the

route where the steering angle of the Super Wing Carrier’s bogie

provided extra manoeuvrability. The challenge was to ensure that

there would be no contact with any part of the blade or the trailer

chassis with the road surface, bridge structures or buildings when

navigating several sections of the route. This is where capabilities

of the Super Wing Carriers to raise the trailer height came into

action, allowing our Team to raise the height of both the front and

the rear of the trailer, resulting in each of the blades oversailing the

embankments and stone parapets when crossing the bridges en-

route. By employing the capabilities of these trailers our Teamwere

able to remove the need for further, more costly modifications, and

ensure that each of the seventy-eight 52metre blades would safely

arrive on site.

Beginning in July, the 18 week delivery schedule is now complete.

Following an agreed timetable of 1.5 turbines per week, our Teams

systematically transported each of the 494 cargoes from their

portside location direct to the delivery site. Working on amulti-port

strategy with components arriving at the Port of Grangemouth and

King George V Dock, the Collett Team have undertaken all ship’s

discharge and stevedoring duties, port storage, extensive planning

and delivery for each complete turbine.

Deliveries to the site, which lies three miles south of Strathaven,

South Lanarkshire, are now completed and construction of the

wind farm is well underway. Kype Muir Wind Farm is the flagship

development of Banks Renewables.

Delivering Kype Muir Wind Farm